Newsletter 11/26
| Issue #11

Even with a shortened holiday week, exciting progress continues at the Paddle Club! Our team has begun installation of the kitchen hood, marking a major step forward for the restaurant build-out. Mbrico tile installation is also underway on the sun deck, bringing us closer to sun filled days next season. In addition, the fire main…

Read More >
Newsletter 11/21
| Issue #10

Exciting momentum continues at Somers Point Paddle Club! Our bar is now being framed inside the restaurant, bringing the social hub of the club to life. Windows have been installed on the main building, giving shape to the space and showcasing those beautiful views. Outside, construction on the ramp to the paddle club is underway…

Read More >
Newsletter 11/14
| Issue #9

Exciting progress continues as we bring the Paddle Club to life! All rough plumbing and framing are complete, and our team has started crafting the bar for the restaurant. Window installation is scheduled for next week, and IPE decking is currently being installed, adding a beautiful finish to our outdoor spaces. Even more exciting news…

Read More >
View of the Somers Point Paddle Club from the water.
Newsletter 11/7
| Issue #8

Exciting milestones continue at the Somers Point Paddle Club! Rough plumbing is now complete, and building framing is nearing the finish line as the structure truly begins to take shape. Crews are preparing to begin window installation on Monday — another big step forward in bringing the clubhouse to life. Behind the scenes, we’re also…

Read More >
Newsletter 10/31
| Issue #7

Progress continues on site as our team moves steadily through the next phase of the build. Each week brings us closer to seeing the full vision come to life. The main building is now fully sheathed, marking another exciting milestone! The exterior end wall for our dining room is currently being framed, giving shape to…

Read More >
Newsletter 10/24
| Issue #6

Exciting progress continues at the Somers Point Paddle Club! The main building now has all roof rafters installed, and sheathing is almost complete. Over at the bar and restaurant, roof rafters are also being set in place. With these major structural elements coming together, you can really start to see the overall shape of the…

Read More >
Newsletter 10/17
| Issue #5

The Pools Are Complete! After a slight setback from last weekend’s nor’easter, our team dedicated three productive days to gunite work, successfully bringing the pools to completion. As the framing for the waterfalls approaches its final stages, the pool area is starting to embody the resort-style ambiance we’ve all been eagerly awaiting! In other areas…

Read More >
Newsletter 10/10
| Issue #4

Progress is being made at the Somers Point Paddle Club! The restaurant and bar now have their flat roof sheathing in place, and the dormer roof rafters have been set on the main building — home to our kitchen, offices, and restrooms. Each week, the property continues to take on more of its final shape….

Read More >
Newsletter 10/3
| Issue #3

Exciting progress continues at the Somers Point Paddle Club. The bar and restaurant have received all structural posts and beams, with more development planned in the coming week. The main building—home to the kitchen, office, and restrooms—is now rising with structural walls going up on the second deck level as crews work toward the roof….

Read More >
Newsletter 9/26
| Issue #2

Framing is underway for our Bar & Restaurant, and the structure is beginning to take shape—making it easier to visualize the exciting space to come. The second floor of the building is also coming together, adding another layer of progress to the project. Meanwhile, work continues on our pools and spas, where steel reinforcement is…

Read More >